Automotive Manufacturing Facility — Tangier Automotive City

Location
Tanger Automotive City (TAC)
Year
2018
Floor area
18 000 m²
Mission
Built-to-Suit • Ingénierie • Coordination globale TCE
Automotive Manufacturing Facility — Tangier Automotive City

Context & client needs

As part of its North African expansion strategy, TE Connectivity initiated the construction of a state-of-the-art manufacturing plant dedicated to high-precision automotive wiring and connectors inside Tangier Automotive City (TAC).

The operational challenge

Deliver an industrial manufacturing complex meeting TE's global standards under an exceptionally aggressive timeline (7 months, April to November 2018), requiring overlapping civil engineering, technical utilities, and machine transfer preparation.

Universal Integration scope of work

Full Built-to-Suit integration: bulk earthworks, structural concrete, long-span structural steel framing, NFPA-certified sprinkler networks, MV/LV power infrastructure, centralized compressed air, anti-static epoxy flooring, and executive office fit-out.

Solutions & systems delivered

Architectural design and structural engineering optimized for natural illumination and thermal comfort
Triple-shift construction scheduling ensuring critical machinery arrival milestone in October
High-flatness anti-static epoxy flooring suitable for AGV and wire-guided logistics
Dedicated 22 kV electrical substation with immediate-start emergency backup generators
Looped compressed air network with 0.01 µm oil-free filtration for precision connector injection molding

Milestones & site timeline

  1. Technical Studies & Earthworks

    Avril 2018

    Master layout validation, structural calculations, and mass earthworks platforms.

  2. Civil Engineering & Structural Steel

    Juin 2018

    Long-span steel framing erection, building envelope, and roof weatherproofing.

  3. Technical Utilities & Networks

    Août 2018

    Sprinkler pipe fitting, MV/LV substations, compressed air loop, and high-spec epoxy screeds.

  4. Machinery Influx & Commissioning

    Octobre - Novembre 2018

    Transfer of initial injection molding lines, utilities connection, and operational launch.

Outcome & measured performance

Facility successfully delivered within the contractual 7-month schedule. First-pass production line qualification. Zero lost-time incidents recorded across the 210-day construction cycle.

Project case study: scope, responsibilities and documented outcomes.Discuss a similar project

Tell us about your project, even at an early stage.

We will arrange an initial discussion to clarify your requirements and the appropriate scope of support. An NDA can be arranged on request before sensitive documents are shared.